3D Model & Database Progress Towards Resource Estimation
Released
Released
Announcement PDF
ASX Announcement – 25 May 2023
3D MODEL & DATABASE PROGRESS TOWARDS
RESOURCE ESTIMATION AT SAN JOSE MINE
Variscan Mines Limited (“Variscan” or the “Company” or the “Group”) (ASX:VAR) is pleased to report
progress at the San Jose Mine, near Novales, located in Cantabria, northern Spain.
Highlights
•
•
•
•
•
•
Upgrade and expansion of drill-hole database at San Jose Mine; now consists of 983 drillholes for 88,155m
3D model of mineralisation and mine development has been constructed from the improved
database
Modelling confirms thick, high-grade, accessible sulfide zinc-mineralised lenses
Analysis highlights in-mine and near-mine upside and step-out prospective zones for future
exploration
Selected historical diamond drilling results in unmined areas stepping out from the San Jose
Mine:
• S-21:
43.0m @ 4.5% Zn including 6.0m @ 9.6% Zn
• S-162:
20.0m @ 4.0% Zn including 3.2m @ 9.6% Zn
• S-163:
16.8m @ 3.4% Zn including 7.3 m @ 6.5% Zn
• S-161:
16.1m @ 3.5% Zn including 5.9m @ 6.3% Zn
Progressing towards publishing a maiden JORC-compliant Mineral Resource Estimate for the
San Jose Mine
Variscan’s Managing Director & CEO, Stewart Dickson said,
“Following our latest round of successful drilling results and recent fund raising, we’ve completed a
comprehensive review and validation of our drill-hole database in preparation for mineral resource
estimation and a mine re-start concept study at the San Jose Mine.
As a result of this work the quality of the database has improved significantly and highlights the in-mine
and near-mine exploration upside. Underground targets are expected to be drill-tested as soon as
practicable with step-out surface drilling to be conducted in H2 of this year. This in-fill drilling, off the back
of recently reported successful step-out drilling, will address strategic spatial gaps which could yield further
tonnage.
All of these results and activities contribute positively to the delivery of our key objectives; a JORC compliant
mineral resource estimate and the mine re-start concept study at the San Jose Mine”.
ASX:VAR
Web - www.variscan.com.au
Figure 1. 3D Mineralisation and Mine Development Model of San Jose Mine
Key Findings
Following Variscan’s drilling success stepping-out approximately 1,200m north-east along the strike of
the San Jose Mine stopes (refer ASX announcement 2 March 2023), a comprehensive review of the
Company’s data was conducted to refine our geological understanding and construct a mineralisation
model for resource estimation and identification of prospective in-mine and near-mine targets for future
drilling.
The database has been thoroughly reviewed with the Variscan team undertaking significant verification
of data in the mine and on the ground in the surrounding areas. As a result, the database has expanded
and now consists of 983 drill-holes for 88,155m (Appendices 1-8).
From this database, a 3D wireframe-based model of mineralisation and mine development at the San
Jose Mine has been constructed (see Figure 1). The modelling confirms numerous thick, high-grade,
accessible sulphide zinc-mineralised lenses. The Company is in the process of appointing a Competent
Persons to produce a JORC compliant mineral resource estimate.
Exploration & Tonnage Upside Potential
In-Mine
Further modelling produced prospective zones for future exploration and resource tonnage potential
within the San Jose Mine (see Figure 2). It is anticipated that these in-mine, underground targets will be
drill-tested as soon as practicable.
Near-Mine
Having reported high grade zinc assay results from step-out drilling (Drill-hole SB-18: 22.00m @ 8.16%
Zn; Drill-hole SB-19B: 6.0m @ 16.02% Zn) in March 2023, Variscan focused on a review of data
around this unmined area with historical drilling indicating very promising exploration targets and
confirming the significant strike potential of the San Jose mineralised system towards the north-east (see
Figure 3).
Page | 2
ASX Announcement – 25 May 2023
Figure 2. Plan and orientated view of the 3D Mineralisation (green) and Mine Development (grey
and yellow) Model of San Jose Mine together with prospective target zones (blue)
Page | 3
ASX Announcement – 25 May 2023
Figure 3. Exploration Potential – Mineralisation extends on strike, stepping out from the San Jose
Mine
Looking Ahead & Workplan
The Company is now progressing the following activities all of which are focused on the San Jose Mine:
•
•
Delivery of approvals to undertake further surface drilling in and around the San Jose Mine to
test promising exploration targets
Phase 3 underground infill and resource definition drilling
Page | 4
ASX Announcement – 25 May 2023
•
•
•
Publishing a focused JORC-compliant maiden Mineral Resource estimate
Reporting a Mine Re-Start Concept Study
In support of the above activities, the delivery of associated environmental, social and
governance (“ESG”) initiatives
ENDS
This announcement has been approved by the Board and authorised for issue by Mr Stewart Dickson,
Managing Director & CEO, Variscan Mines Limited.
For further information:
Variscan Mines
Stewart Dickson
T: +44 (0) 7799 694195
E: stewart.dickson@variscan.com.au
Media enquiries – The Capital Network
Julia Maguire
T: +61 2 8999 3699
E: julia@thecapitalnetwork.com.au
Notes
Variscan Mines Limited (ASX:VAR) is a growth oriented, natural resources company focused on the
acquisition, exploration and development of high-quality strategic mineral projects. The Company has
compiled a portfolio of high-impact base-metal interests in Spain, Chile and Australia. Its primary focus
is the development of its advanced zinc projects in Spain.
The Company’s name is derived from the Variscan orogeny, which was a geologic mountain building
event caused by Late Paleozoic continental collision between Euramerica (Laurussia) and Gondwana to
form the supercontinent of Pangea.
To learn more, please visit: www.variscan.com.au
Page | 5
ASX Announcement – 25 May 2023
Competent Person Statement
The information in this document that relates to technical information about the Novales-Udias project is
based on, and fairly represents information and supporting documentation compiled and reviewed by
Dr. Mike Mlynarczyk, Principal of the Redstone Exploration Services, a geological consultancy acting as
an external consultant for Variscan Mines. Dr. Mlynarczyk is a Professional Geologist (PGeo) of the
Institute of Geologists of Ireland, and European Geologist (EurGeol) of the European Federation of
Geologists, as well as Fellow of the Society of Economic Geologists (SEG). With over 10 years of fulltime exploration experience in MVT-style zinc-lead systems in several of the world’s leading MVT
provinces, Dr. Mlynarczyk has sufficient experience which is relevant to the style of mineralisation and
type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent
Person as defined in the December 2012 edition of the “Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves” (‘JORC Code’). Dr. Mlynarczyk consents to the inclusion in
the report of the matters based upon the information in the form and context in which it appears.
The information in this document that relates to previous exploration results was prepared pre-2012
JORC code. It is the opinion of Variscan that the exploration data is reliable. Although some of the data
is incomplete, nothing has come to the attention of Variscan that causes it to question the accuracy or
reliability of the historic exploration.
Forward Looking Statements
Forward-looking statements are only predictions and are not guaranteed. They are subject to known
and unknown risks, uncertainties and assumptions, some of which are outside the control of the Company.
Past performance is not necessarily a guide to future performance and no representation or warranty
is made as to the likelihood of achievement or reasonableness of any forward-looking statements or
other forecast. The occurrence of events in the future are subject to risks, uncertainties and other factors
that may cause the Company’s actual results, performance or achievements to differ from those referred
to in this announcement. Given these uncertainties, recipients are cautioned not to place reliance on
forward looking statements. Any forward-looking statements in this announcement speak only at the
date of issue of this announcement. Subject to any continuing obligations under applicable law and the
ASX Listing Rules, the Company, its directors, officers, employees and agents do not give any assurance
or guarantee that the occurrence of the events referred to in this announcement will occur as
contemplated.
Page | 6
ASX Announcement – 25 May 2023
JORC Table 1, Sections 1 and 2
Criteria
JORC Code explanation
Commentary
Sampling
techniques
Nature and quality of sampling
(e.g., cut channels, random chips,
or specific specialised industry
standard measurement tools
appropriate to the minerals under
investigation, such as down hole
gamma sondes, or handheld XRF
instruments, etc). These examples
should not be taken as limiting the
broad meaning of sampling.
Include reference to measures taken
to ensure sample representativity
and the appropriate calibration of
any measurement tools or systems
used.
Aspects of the determination of
mineralisation that are Material to
the Public News release.
In cases where ‘industry standard’
work has been done this would be
relatively simple (e.g., ‘reverse
circulation drilling was used to
obtain 1 m samples from which 3
kg was pulverised to produce a 30
g charge for fire assay’). In other
cases more explanation may be
required, such as where there is
coarse gold that has inherent
sampling problems. Unusual
commodities or mineralisation types
(e.g., submarine nodules) may
warrant disclosure of detailed
information.
Page | 7
The drilling data of the San Jose mine and adjacent area that is
referenced in this news release relates to historical surface and
underground drilling conducted by previous operators, as well as
to the underground and surface drilling conducted in the area by
Variscan Mines in the years 2020-2022. The details of all drill
hole co-ordinates and orientations, as well as matching drill core
assay data are listed in Appendices 1-8. Except for the historical
drillhole information recently added to the database, this
information has already been published in prior news releases,
however, as the detailed re-surveying of all drill collar locations
has produced more accurate data, the full drill hole collar and
drill core assay database is presented in Appendices 1-8, for
consistency. The complete information on the multiple drilling
campaigns of various vintages is obviously very extensive and
can be found in prior ASX press releases by Variscan Mines on
the website www.variscanmines.com.au. What is provided below
is merely a summary.
The historical data used in the preparation of this news release
relates to exploration undertaken by mining companies
operating the Project from the 1950’s to the late 1990’s. This
historical data consists of both underground and surface core
drilling, of which the paper-format core logs and location maps
are held at the School of Mines and Energy Engineering at
Torrelavega, a faculty of the University of Cantabria. The details
of all historical drill hole co-ordinates and orientations, as well as
matching drill core assay data are listed in Appendices 1-4. Full
details of this historical drilling can be found in prior ASX press
releases by Variscan Mines from the following dates: 3 rd Feb
2020, 3rd March 2020, 16th March 2020 and 1st April 2020 on
the website www.variscanmines.com.au.
The recent addition of new historical underground drill holes to
the drilling database results from a thorough survey of all
historical underground drill collars conducted recently by
Variscan Mines. In this survey, the bulk of historical drill collars
were located in minute detail using the data cloud of the 3D laser
survey of the San Jose mine drifts and stopes realized by
Variscan Mines in the years 2020-2022. These collar locations
were then cross-checked with detailed historical mine plans. In
addition, for each drill hole, the drill trace azimuth and inclination
were measured in situ using a Brunton compass and checked
across the historical drill records, for consistency. As a result, of
the total 666 historical underground drill holes inventarised by
Variscan Mines from historical drill records (and totalling
52,148m); the collar locations and drill traces of 634 drill holes
were constrained in very satisfactory detail. The remaining 32
drill holes have incomplete data and cannot be plotted in 3D.
Due to the incomplete nature of the historical drill data and
records, including procedures, a comment on the sample
representativity or calibration of measurement tools or systems
used by historical workers cannot be made. Further comments
regarding specific components of the historical drilling are
provided in subsequent sections of this table. The historical data
cannot be considered ‘industry standard’ by modern standards.
It has been assumed that the assays are representative of
technology available at the time, but no reliance has been put
on it. It is understood that most if not all assaying carried out by
Asturiana de Zinc Sociedad Anonima / Real Compania Asturiana
de Minas (the main historical operators of the project) was
carried out at their own laboratory (Laboratorio Central) in
Torres, and that the practice of assaying half-core was the
general rule.
ASX Announcement – 25 May 2023
Criteria
JORC Code explanation
Commentary
Drilling
techniques
Drill type (e.g., core, reverse
circulation, open-hole hammer,
rotary air blast, auger, Bangka,
sonic, etc) and details (e.g., core
diameter, triple or standard tube,
depth of diamond tails, facesampling bit or other type, whether
core is oriented and if so, by what
method, etc).
Drill sample
recovery
Page | 8
Method of recording and assessing
core and chip sample recoveries
and results assessed.
Variscan Mines underground drilling data referenced in this news
release comprises 119 diamond drill holes (totaling 3,848m),
plus 41 additional holes (totalling 599m) obtained using a
portable Hilti drill, all of which were core drilling. The details of
Variscan’s underground drilling campaigns can be found in
Appendices 5-6, as well as in prior ASX press releases by
Variscan Mines from the following dates: 9th March 2021, 25th
May 2021, 15th June 2021, 4th August 2021, 15th March 2022,
7th July 2022, 25th August 2022 on the website
www.variscanmines.com.au.
In addition, limited surface diamond drilling was conducted by
Variscan Mines in the area discussed in this news release. This
consisted of 3 surface drill holes (totalling 322m of core drilling),
and the full details can be found in Appendices 7-8, as well as
in Variscan Mines’ ASX press release from 2nd March 2023.
All diamond drilling of Variscan Mines has been sampled with
industry best practice methods (diamond drilled core cut along
its length to produce half core) and the samples were sent to the
accredited ALS Seville laboratory for analysis. The samples are
considered representative and include waste intervals on the
periphery of mineralised intersections. It is assumed that the
equipment used was calibrated correctly as per the internal
SOP’s at ALS.
The bulk of Variscan Mines drillholes consist of underground
diamond drillholes located in the San Jose Mine, with an
additional 4 short holes drilled inside the neighboring nearsurface artisanal mines of Eucaliptal and Eloisa, and 3 surface
diamond drill holes in the vicinity of the mine’s entrance, south of
the Novales village. All of these drill holes were sampled as half
core from 15cm to 1.40m sample length (average 1.00m), with
at least a single 1m sample either side to cover the periphery of
the mineralised intersection. The analytical method used by ALS
was Zn-OG62h for Zinc and Pb-OG62h for Lead, as well as ZnAA07 for non-sulphide (‘oxide’) zinc. These are considered
appropriate for the deposit type.
The Variscan Mines drillholes referred to in this news release are
either underground diamond drillholes (core) completed using a
Hagby Onram 100 rig, an Atlas Copco Diamec 252 rig and a
Hilti portable drill, all at a core diameter of 40.7mm (BQTK) or
surface diamond drillholes (core) completed using a Rolatec RL1000 drill rig, at a core diameter of PQ and HQ.
Neither Variscan Mines drillholes nor the historical drillholes have
employed oriented core methods.
Details of Variscan Mines drilling referenced in this document can
be found in prior ASX press releases by Variscan Mines from 9th
March 2021, 25th May 2021, 15th June 2021, 4th August 2021,
15th March 2022, 7th July 2022, 25th August 2022, and 2nd
March 2023 on the website www.variscanmines.com.au.
The historic surface and underground drilling is understood to be
all core drilling. No details of the drilling techniques employed
have been identified in the historic data. This includes reference
to core diameter(s), core orientation methods, and downhole
survey data. No records of the type of drill rig used have been
identified.
Details of the historical drilling referenced in this document can
be found in prior ASX press releases by Variscan Mines from the
following dates: 3rd Feb 2020, 3rd March 2020, 16th March 2020
and 1st April 2020 on the website www.variscanmines.com.au
Core recovery for the Variscan Mines drillholes has been typically
high >90%, as observed by drillers and geologists, this data has
been formally recorded for all drillholes at this time, as it forms
ASX Announcement – 25 May 2023
Criteria
JORC Code explanation
Commentary
Measures taken to maximise sample
recovery and ensure representative
nature of the samples.
Whether a relationship exists
between sample recovery and
grade and whether sample bias
may have occurred due to
preferential loss/gain of
fine/coarse material.
part of the detailed logging. The lowest recovery recorded for
an entire drillhole to date is 74.7% mean recovery; however, this
is totally anomalous compared to the remaining holes.
No other methods have been used to maximise sample recovery;
however, with recovery >90% reported for nearly all the holes
referenced in this news release the methods currently employed
appear sufficient. The relationship between sample recovery and
grade has not been assessed thus far.
No records of drill core recovery have been identified for most of
the historical drillholes and no historical drill core has been
preserved. Where recovery data is available, it typically includes
recoveries >90%, however, recoveries as low as 60% have also
been recorded. Given the absence of core recovery data, it is not
possible to assess the potential relationship between sample
recovery and grade. The absence of drill recovery data means
that the referenced grades may be subject to either over- or
under-estimation. No assessment or estimation of these effects has
been made due to the lack of detailed data.
Details of historical drilling referenced in this document can be
found in prior ASX press releases by Variscan Mines from the
following dates: 3rd Feb 2020, 3rd March 2020, 16th March 2020
and 1st April 2020 on the website www.variscanmines.com.au
Logging
Whether core and chip samples have
been geologically and
geotechnically logged to a level of
detail to support appropriate
Mineral Resource estimation, mining
studies and metallurgical studies.
Whether logging is qualitative or
quantitative in nature. Core (or
costean, channel, etc) photography.
The total length and percentage of
the relevant intersections logged.
Sub-sampling
techniques and
sample
preparation
If core, whether cut or sawn and
whether quarter, half or all core
taken.
If non-core, whether riffled, tube
sampled, rotary split, etc. and
whether sampled wet or dry.
For all sample types, the nature,
quality and appropriateness of the
sample preparation technique.
Quality control procedures adopted
for all sub-sampling stages to
maximise representativity of
samples.
Measures taken to ensure that the
sampling is representative of the insitu material collected, including for
instance results for field
duplicate/second-half sampling.
Whether sample sizes are
appropriate to the grain size of the
Detailed geological and geotechnical logging has been carried
out for all of Variscan Mines drillholes. Currently there is sufficient
geotechnical and geological logging data to support a Mineral
Resource estimate. However, mining studies and metallurgical
testwork are still required.
Total percentage of Variscan Mines drill holes that have been
logged for lithology, veins, alteration, and mineralisation is 100%
and the total percentage of new drillholes that has detailed
recovery and geotechnical logging is 100% at this stage (based
on all logs available). All drillholes were photographed before
and after cutting core.
No geotechnical logs have been identified for historical drillholes,
but the bulk of geological logs were retrieved and digitised, with
the vast majority of historical holes having assay and lithology
downhole data. No core photography has been identified.
Details of any historical drilling referenced in this document can
be found in prior ASX press releases by Variscan Mines from the
following dates: 3rd Feb 2020, 3rd March 2020, 16th March 2020
and 1st April 2020 on the website www.variscanmines.com.au
The Variscan Mines drillholes have been sampled using industry
procedures for logging (of mineralisation), sampling and QAQC
that are definitely appropriate for this project..
Variscan Mines samples were selected by geologists based on the
logging of mineralised intervals, drill core was cut using a rotary
diamond saw along the long axis in halves. Samples were
preferred at 1m lengths, although they were permitted flexibility
from 15cm to 1.40m sample lengths, typically where geological
boundaries exist. In the Variscan SOP for sampling drill core it is
stated that a minimum of three samples have to be taken for any
mineralised intersection, the first sample will encompass the
mineralised zone and the other two samples will be selected either
side to ensure waste intervals were sampled to define the
boundaries of mineralisation. Additionally, when a separate
geological zone or rubble or broken core begins, a new sample
will be taken, and when solid core resumes the next samples will
be selected. In zones of poor recovery <50% the default sample
interval will be the drillers depth markers. The nature and quality
of sampling techniques are considered appropriate for this
deposit and drilling type.
Page | 9
ASX Announcement – 25 May 2023
Criteria
JORC Code explanation
material being sampled.
Quality of assay
data and
laboratory tests
The nature, quality and
appropriateness of the assaying and
laboratory procedures used and
whether the technique is considered
partial or total.
For geophysical tools,
spectrometers, handheld XRF
instruments, etc, the parameters used
in determining the analysis including
instrument make and model, reading
times, calibrations factors applied
and their derivation, etc.
Nature of quality control procedures
adopted (eg standards, blanks,
duplicates, external laboratory
checks) and whether acceptable
levels of accuracy (ie lack of bias)
and precision have been established.
Verification of
sampling and
assaying
The verification of significant
intersections by either independent
or alternative company personnel.
The use of twinned holes.
Documentation of primary data,
data entry procedures, data
verification, data storage (physical
and electronic) protocols.
Page | 10
Commentary
All Variscan Mines half core samples were sent directly to the ALS
Seville laboratory for preparation and subsequent analysis
according to industry standards with crushing, pulverizing and
splitting prior to sample analysis. The sample sizes taken for the
drilling reported are considered suitable for the deposit type and
style of mineralisation at this stage of exploration.
The historical approach to sampling appears selective, mainly
guided by visual observation and clearly neither low-grade
mineralisation, trace mineralisation, nor “apparent” waste were
sampled. No details of the sample preparation techniques have
been identified from the historical records, and no supporting
sampling procedures have been identified. In many cases, it is
not known whether ¼, ½ or whole core was submitted for
analysis, though assaying half-core was practised as a rule by
Asturiana de Zinc Sociedad Anonima, with sampling intervals
normally ranging from 0.5 to 3.0m. Longer assay sample
intervals (in some cases attaining 10m) evidenced in the historic
logs are interpreted to represent sample composites, but no
detailed explanations on the method used for compositing are
available. In the absence of most data, and other data related
to the sub-sampling techniques and sample preparation, no
comment on the appropriateness of the sample preparation
techniques can been made.
No evidence of Quality Control procedures has been identified
for the historical holes. This includes evidence of field duplicates
or other current industry standard quality control procedures, such
as Certified Reference Materials and blanks. In the absence of
sample size data, no comment on whether the sample size is
appropriate to the grain size of the sampled material can been
made for these historical drillholes.
For the drilling conducted by Variscan Mines the sampling is
considered partial as half core remains. The laboratory is
accredited (ALS Seville) and the techniques for Zn/Pb (ZnOG62h, Pb-OG62h, and Zn-AA07) are considered suitable for
the elements in question.
QAQC Procedures adopted by Variscan Mines for drill core
assaying include the use of proper CRMs (OREAS 134B, OREAS
133A, and OREAS 130; i.e., high, medium, and low grade)
inserted into the sample stream, along with coarse/pulp blanks
and internal duplicates, where a single coarsely crushed sample
is further processed as two separate splits. The frequency and
variety of QAQC samples inserted into the sample stream has
typically been in the order of 10-20% and is considered fully
compliant with industry’s best practice, with the samples reviewed
showing good repeatability.
In the case of historical drilling, no descriptions of the assaying
and laboratory procedures used have been found. It is unknown
whether the techniques used were partial or total, though there is
evidence that at least one of the main project operators, Asturiana
de Zinc Sociedad Anonima, as a general rule assayed half core.
No descriptions of quality control procedures adopted for
historical drilling by the laboratory, nor any results of Quality
Control data have been identified. Therefore, no comment can be
made on whether acceptable accuracy or precision of results have
been established.
The analytical processes related to Variscan Mines’ drilling
campaigns have been supervised by senior ALS staff experienced
in mineral assaying.
Most of Variscan Mines drillholes consist of underground diamond
drillholes located within the San Jose Mine, with an additional 4
short holes drilled inside the neighbouring near-surface artisanal
mines of Eucaliptal and Eloisa, and 3 surface diamond drill holes
in the vicinity of the mine’s entrance, south of the Novales village.
ASX Announcement – 25 May 2023
Criteria
JORC Code explanation
Discuss any adjustment to assay
data.
Commentary
Location of data
points
Accuracy and quality of surveys used
to locate drill holes (collar and
down-hole surveys), trenches, mine
workings and other locations used in
Mineral Resource estimation.
Specification of the grid system
used.
Quality and adequacy of
topographic control.
Page | 11
Some of the holes are located near existing historical drillholes,
however, they cannot be considered twinned holes at this stage.
The data for all of Variscan Mines’ drilling campaigns are stored
in excel and all assay certificates and final assay results provided
by ALS Seville have been reviewed.
In the case of historical drilling campaigns, owing to the lack of
preserved drill core, it has not been possible to verify significant
intersections. It is not known whether verification of intersections
was undertaken by previous operators at the time of drilling. The
historical data does not include any twinned holes. No
documentation or records of primary data (other than paper
logs), data entry procedures, data verification, data storage
(physical and electronic) protocols have been identified. Historical
records consist largely of handwritten drill hole summaries. This
data was identified and transcribed to Microsoft Excel © and then
imported into Leapfrog Geo and Datamine Studio RM for drill
hole database validation, significant intersections, and 3D
viewing. Variscan intends to transfer this data to an industry
standard drill hole database during ongoing exploration of the
project.
Given the absence of detailed historical information relating to
the historical assay data, no adjustment to the assay data has
been made. The data has been reported as it was recorded in
the original documentation. Variscan have no reason to disbelieve
the data as presented in the historical logs, however, understand
the limitations of the data for use in reliable and classified mineral
resource estimations going forward until assay verification has
been achieved to a satisfactory standard.
Of the total 666 historical underground drill holes inventarised by
Variscan Mines from historical drill records (and totalling
52,148m); the collar locations and drill