Quarterly Activities and Cash Flow Reports
Released
Released
Announcement PDF
March 2024 Quarterly Report | 30 April 2024
Variscan Mines Limited (ASX:VAR)
High-grade Zinc Assay results from recent drilling campaign
Revised Structural and Geological assessment highlights continuity and
new drill targets at San Jose Mine
Lease of San Jose Mine Site & Facilities Extended
Award of new licenses substantially increases size of
Novales-Udias Project
Highlights during the Quarter
•
•
•
•
•
•
•
•
High grade zinc assay results from current underground drilling campaign
Selected drilling results:
o NDDT027 14.5 m @ 8.93% Zn, 0.50% Pb
o NDDT029 11.6 m @ 8.43% Zn, 1.61% Pb
o NDDT026 7.0 m @ 5.30% Zn, 0.04% Pb
o NDDT028 6.0 m @ 6.59% Zn, 0.62% Pb
o NDDT020 3.0 m @ 5.55% Zn, 0.41% Pb
Existing Mineral Resource Estimate model is well supported by these infill drill intercepts
Comprehensive geological assessment and structural targeting study completed by worldrenowned expert, Dr. Brett Davis
Work has resulted in a significantly improved understanding of the controls on multi-phase ZnPb mineralization at San Jose
High-priority regional targets will be tested as part of the planned surface drilling campaign for
2024
Signed a new agreement to lease the San Jose Mine site and facilities for a period of 3 years,
extendable up to 6 years
Site is already permitted for mineral exploration, development and mining activities
Subsequent to the end of the Quarter
• 5 new licences awarded, with an area of 36.66 km2, are immediately adjacent to the existing
San Jose and Buenahora tenements
• 70% increase to the land package of the newly enlarged Novales-Udias Project
Variscan Mines Limited (ASX:VAR) (“Variscan” or “the Company”) is pleased to announce its Appendix 5B
for the quarter ended 31 March 2024 and an accompanying operational update for this period.
Variscan’s Managing Director & CEO, Stewart Dickson said,
“Variscan’s March 2024 quarter was a very productive one, which saw further development of the structural
and geological knowledge of the San Jose Mine, as well as more high-grade results from infill drilling to
support the existing Mineral Resource Estimate.
Additionally, we achieved several important hurdles, namely the extension of the lease of the San Jose Mine
Site and infrastructure facilities and, shortly after the end of the quarter, were awarded 5 additional licenses
adjacent to the Novales-Udias project which has increased the land holding. Most importantly, these licenses
cover the NE trend to approximately 12km in strike length.
The drilling permits over these new licenses have already been submitted, and we look forward to reporting
to shareholders the results of future programs on these exciting prospects.”
OPERATIONS REVIEW
Variscan’s exploration and development strategy for the Novales-Udias Project continued to be advanced
over the March 2024 quarter.
Spain – Novales-Udias Zinc Project
The Novales-Udias Project is located in the Basque-Cantabrian Basin, some 30km southwest from the
regional capital, Santander. The project is centred around the former producing San Jose underground mine
with a large surrounding area of exploration opportunities over the 9km Novales Trend, which includes a
number of satellite underground and surface workings.
This project, which is highly prospective across multiple fronts and located in close proximity to both major
infrastructure requirements and zinc consumers, continued to be the major focus of Variscan’s exploration
and development activities over the three months to 31 March 2024.
Geological and structural controls point to new targets within the San Jose Mine
In December of 2023, Variscan commissioned Dr. Brett Davis, a highly respected independent consultant,
who is widely regarded in the exploration and mining industry for his application of applied structural
geology, to work alongside the Company’s in-country technical team as well as Dr. Frank Bierlein, a Variscan
Non-Executive Director. This work was completed during the quarter and announced to the market on 19
February 2024.
The fieldwork identified four principal elements that are critical in controlling fluid ingress and mineralization
at San Jose, in addition to the favorable composition of the ore-hosting dolostone sequence. As illustrated in
Figures 1 to 3, these are:
•
•
•
•
Bedding orientation
S1 - the axial plane of conspicuous macroscale folds (products of the D1 stress regime)
D2 faults, in particular E-W trending transfer-style structures
S2 (typically a fracture cleavage)
2
Figure 1. Approximate orientation of the dominant D1 and D2 structures overlaid with existing mine
development at the San Jose Mine
Figure 2. Interpreted tectonic evolution of the structurally controlled -mineralization-fluid flow system at San
Jose
3
The extrapolation of structural trends highlights priority exploration targets, in particular where D1 and D2
structures intersect. These zones of increased permeability favoured the deposition of Zn-Pb mineralization
and as such are considered a high priority target for in-mine drill-testing (see Figure 3).
Figure 3. Extrapolation of structural trends in the San Jose Mine, based on the relative timing of
mineralization associated with the development of S1 and S2 planes, respectively; these features are major
contributors to the permeability network, and are delineated by structures exposed in mine development
and by zones of historical exploitation.
4
High-grade Zn assay results received
In March 2024, Variscan announced the results of continuing underground drilling in the San Jose Mine (refer
ASX announcement 4 March 2024). This underground drilling program has been upscaled in duration and
meterage. It is focused on expanding known zones of mineralization and discovering new zones with a view
to supporting an upgraded Mineral Resource Estimate in the future. Ongoing drilling is testing:
1.
2.
3.
prospective zones that have been identified from the development of our 3D modelling;
structures within and beyond the defined Mineral Resource Estimate (“MRE”) area which have seen
limited exploration drilling; and
above or below previously-mined stopes where historical production had ceased
The drilling results reported here have targeted areas of known Zn-Pb structures that were previously
underexplored or underexploited. The high-grade intercepts are mainly associated with the La Caseta Trend
within the Central Zone of the San Jose Mine.
Figure 4. Plan view of new drill-hole data over the Central Zone, San Jose Mine
5
Current drilling is testing new structural targets in the San Jose Mine
The recently released geological assessment and structural targeting study (refer ASX announcement 19
February 2024) resulted in a significantly improved understanding of the controls on multi-phase Zn-Pb
mineralization at the San Jose Mine.
The new assay results from the La Caseta trend were obtained from the intercept of a prominent D2
structure. Newly identified targets within the San Jose Mine arising from the study are being drill-tested as
part of the ongoing underground drilling campaign. In particular the cross-cutting D2 structure linking Stope
200 and the La Caseta trend is being drilled currently. This target area lies outside of the existing MRE
model.
Figure 5. Diamond Drill Core from NDDT029 illustrating interval of massive sphalerite hosted in dolostone
Note: Hole depth shown is from 0m to 12.5m
6
Key assay results from this drilling program included:
o
o
o
o
o
NDDT027
NDDT029
NDDT026
NDDT028
NDDT020
14.5 m @ 8.93% Zn, 0.50% Pb
11.6 m @ 8.43% Zn, 1.61% Pb
7.0 m @ 5.30% Zn, 0.04% Pb
6.0 m @ 6.59% Zn, 0.62% Pb
3.0 m @ 5.55% Zn, 0.41% Pb
Drilling has continued to return thick intercepts of significant zinc mineralization and consequently expand
and infill zones of high-grade zinc mineralization within the Central Zone of the San Jose Mine
Figure 6. 3D view of drill-hole locations testing D2 structural targets between Stope 200 and the La Caseta
Trend in the San Jose Mine
San Jose Mine Site Lease
Shortly after the acquisition of the Spanish zinc projects in 2019 the Company entered into certain
agreements with Hispanibal S.L. (“HSP”) (refer ASX announcement 26 September 2019) which included a
Cooperation & Partnership Agreement. Under the terms of the Cooperation & Partnership Agreement, HSP
agreed for Variscan to use the San Jose mine site and its facilities for a 4 year period for nil consideration.
During which time Variscan invested in the upgrade of site and its buildings, especially its offices, core logging
and storage facilities.
The Company has now signed a new agreement to lease the site and facilities for a period of 3 years and
extendable up to 6 years, at the option of Variscan, at a competitive, commercial rate in line with prevailing
local norms for industrial sites.
7
San Jose Mine Site with infrastructure in place is advantageous
The site confers a number of advantages to Variscan:
•
•
•
•
•
•
•
•
31,199m2 site adjacent to the village of Novales is already permitted for use for mineral
exploration, development and mining activities (see Figures 7 & 8)
Access to the main portal of the underground San Jose Mine;
The site comprises 5 permanent buildings. The total area of constructed buildings is 1,157m2
with the ability add more warehouse area if required;
The property has existing water supply, which is being upgraded and single-phase power. The
site was previously supplied with overhead 3-phase power, re-connection will be assessed during
Mine Re-Start Study work;
Excellent core logging and storage facilities established (see Figure 9);
Direct access via sealed roads capable of taking heavy goods vehicles;
Site is within trucking distance (~145km) from the San Juan de Nieva zinc smelter operated by
Asturiana de Zinc (100% owned by Glencore).
Site is ~30km southwest from the regional capital, Santander which has an international airport
and a deep water port with freight terminals.
Figure 7. Aerial view of San Jose Mine Site & Facilities
8
Figure 8. Ground view of San Jose Mine Site & Facilities (looking North)
Figure 9. San Jose Mine Site Core Logging
9
Figure 10. San Jose Mine site proximal to San Juan Smelter and regional capital, Santander
New Licences Awarded
Shortly after the end of the quarter on 8 April 2024, Variscan announced the award of new exploration
licenses within the Novales-Udias region. The 5 new licences, together termed as the ‘Caborredondo’
licences, (see Figure 11 and Table 1) are for a three year period and can be extended for an additional three
years by the Ministry of Industry subject to compliance by filing a report of results of the exploration program.
Formal ratification of the licences will be made following the review of certain supplementary information to
be supplied by Variscan, including annual work plans, to the satisfaction of the Government of Cantabria. The
award of the licences does not carry a minimum financial spending commitment.
Figure 11. Map of enlarged licence areas including the Caborredondo licences
10
Table 1. Licence areas awarded comprising the Caborredondo Licences
Licence Area
Size (km2)
Esperanza
34.44
Estela
0.56
Elena
0.28
Candela
1.11
Valeria
0.28
Total
36.66
Geology and Mineralization
The principal geological feature is a wide synclinal structure that characterizes the western end of the BasqueCantabrian Basin, named the Santillana syncline, striking NE-SW. The Caborredondo Licences cover a
significant part of the Santillana syncline, where multiple zinc ore deposits occur. The former producing
world-class Reocín Mine is located on the southeast flank of the syncline, whereas the newly gained ground
occupies a symmetrical position on the northwest flank of the syncline, where dolomitic alteration and zinc
mineralization are well developed in the same Gargasian (Upper Aptian) carbonate beds as found at the
nearby Reocín Mine.
The Reocín deposit is one of the largest known stratabound, carbonate-hosted, zinc-lead deposits in Europe.
The total metal endowment of the deposit, including past production and remaining reserves, is c. 87 Mt of
ore grading 11 percent Zn and 1 percent Pb. (Velasco, 2003). 1
The large licence area (34.4km2) to the east (auspiciously named ‘Esperanza’, i.e., ‘hope’ in Spanish) has
extended the Novales-Udias Trend of zinc mineralization to approximately 12km in length. The Novales-Udias
Trend is characterised by the former producing, sizeable San Jose and Udias Mines, as well as numerous
historical small-scale mines and workings. The Esperanza licence hosts over a dozen historical small-scale
mines and workings and has multiple positive exploration data, whereas the small licence in the centre of
the already held San Jose mining licence (named ‘Estela’) hosts the main shaft of the Udias mine (Pozo
Madroño) and some major underground developments of the historical Udias Mine.
1
Velasco, F., Herrero, J.M., Yusta, I., Alonso, J.A., Seebold, I. and Leach, D., (2003) ‘Geology and Geochemistry of the
Reocin Zinc-Lead Deposit, Basque-Cantabrian Basin, Northern Spain’ Econ. Geol. v.98, pp. 1371-1396.
11
Figure 12. Map of enlarged licence areas and underlying geology
De-risked exploration opportunity to scale-up the Novales-Udias Project
The new licence areas have been explored to a limited extent by Asturiana de Zinc in the 1980's. The data
uncovered to date indicates there is an opportunity to grow the scale of the tonnage of the Novales-Udias
Project.
Historical drilling
The Variscan exploration team have identified the location of 53 drillholes over the Esperanza licence area.
Early work has confirmed historical drill intercepts over the licence areas that include (refer ASX
announcement 8 April 2024):
•
•
•
•
•
•
DDH S-21: 6.0m @ 9.62% Zn
DDH S-163: 7.3m @ 6.50% Zn
DDH S-162: 3.2m @ 9.57% Zn
DDH S-162: 3.3m @ 6.33% Zn
DDH S-162: 2.0m @ 6.73% Zn
DDH S-100: 1.0m @ 6.28% Zn
12
A large amount of regional historical archives, including drillhole data, is currently under review and will be
reported as soon as practicable.
It is very clear that the Esperanza licence area hosts the eastern part of the high-zinc-grade Novales Trend,
which is open to the north-east, and also that the favourable dolomitic strata on the western limb of the
Santillana syncline and dipping east are prime exploration ground for large-scale ‘Reocin-type’ zinc systems,
with all the tell-tale exploration vectoring signs being very encouraging for drilling this area.
Geochemistry
Limited geochemical sampling was conducted by Asturiana de Zinc in the 1980s and shows high grade zinc
results extending northeast from the area of the San Jose Mine and highlighting the extensive length and
width of the Novales Trend as it outcrops on surface (see Figure 13). The more significant zinc anomalies
typically range 4,000 – 9,000 ppm Zn (maximum 33,600 ppm Zn) and 380 – 2280 ppm Pb, making for
compelling drill targets.
Figure 13. Geochemistry shows continuity from San Jose eastwards into the new Esperanza Licence.
13
Former mine workings
The new licence areas also host numerous historical near-surface and underground workings for zinc, such
as the historical small-scale mines of Margarita, Emilia, Soberbia, Pedroso, Cualquiercosa, and a number of
unnamed ones. An area of notable significance is the Estela licence, which hosts the main shaft of the Udias
Mine (Pozo Madroño) and some major underground developments in the central part of the historical Udias
Mine. The award of this licence infills a previous gap in the San Jose mining licence.
Spain – Guajaraz Zinc Project
The Guajaraz Project is a prospective brown-field zinc-rich polymetallic opportunity with known mineral
occurrences. The project is located in the highly mineralised Central Zone of the Iberian Massif, which ranks
as one of the most mineralised geological units globally and represents the internal zone of the prolific
European Variscan Orogenic belt.
The project area lies within a primary igneous and metamorphic crystalline plateau that hosts abundant
hydrothermal vein networks that have a long history of exploration. Brittle-fault related vein and silicified
breccia ore deposits are of the BPGC type (zinc-galena-pyrite-chalcopyrite).
While the main focus over the March 2024 quarter was again the exploration and eventual development of
the Novales-Udias project, Guajaraz remains a core asset in Variscan’s portfolio.
In late October 2023, Variscan announced that the Consejería de Desarrollo Sostenible (Department of
Sustainable Development) of the Junta de Comunidades de CastillaLa Mancha (the regional Government of
Castile-La Mancha) had approved a 3-year extension of the “Guajaraz” Permiso de Investigación (Exploration
License), located in central Spain (see ASX announcement dated 26 October 2023).
The design of a future long-term work program for the Guajaraz Project, which will extend across the 2023
through 2026 lifespan of the now renewed Exploration License, includes:
•
•
•
soil geochemistry.
geophysical survey.
initial drilling campaign.
14
PROJECT SUMMARIES
Spain – Zinc-rich Novales-Udias Project
The Novales-Udias Project is located in the Basque-Cantabrian Basin, some 30 kilometres southwest from
the regional capital, Santander. The project is centred around the former producing San Jose underground
mine with a large surrounding area of exploration opportunities for a number of satellite deposits based on
underground and surface workings, our substantial database of historic drilling and multiple areas of zinc
anomalism identified from recent and historic geochemical surveys. Variscan has defined the NE-SW Novales
Trend over 9 kilometres with a parallel mineralised trend over at least 3 kilometres of strike.
Key highlights of the Novales-Udias Project:
•
•
•
•
•
•
•
•
•
•
•
•
Near term zinc production opportunity
Large tenement holding of 68.3 km2 (including several granted mining tenements)
Regional exploration potential for another discovery analogous to Reocin (total past production and
remaining resource 62Mt @ 8.7% Zn and 1.0% Pb 2,3)
San Jose Mine is within trucking distance of the Glencore zinc smelter in the neighboring region of
Asturias
Classic MVT carbonate hosted Zn-Pb deposits
Historic production of high-grade zinc; average grade reported as around 7% Zn 4
Simple mineralogy of sphalerite – galena – calamine
Ore is strata-bound, epigenetic, lenticular and sub-horizontal
Reported historic production of super high grade ‘bolsas’ (ore bags) commonly 10-20% Zn and in
some instances +30% Zn 5
Assay results of targeted grab samples taken from within the underground Novales Mine recorded
31.83% Zn and 62.3% Pb 6
Access and infrastructure all in place
Local community and government support due to historic mining activity
1 Velasco, F., Herrero, J.M., Yusta, I., Alonso, J.A., Seebold, I. and Leach, D., 2003 - Geology and Geochemistry of the
Reocin Zinc-Lead Deposit, BasqueCantabrian Basin, Northern Spain: in Econ. Geol. v.98, pp. 1371-1396.
3
Cautionary Statement: references in this announcement to the publicly quoted resource tonnes and grade of the
Project are historical and foreign in nature and not reported in accordance with the JORC Code 2012, or the categories
of mineralisation as defined in the JORC Code 2012. A competent person has not completed sufficient work to classify
the resource estimate as mineral resources or ore reserves in accordance with the JORC Code 2012. It is uncertain that
following evaluation and/or further exploration work that the foreign/historic resource estimates of mineralisation
will be able to be reported as mineral resources or ore reserves in accordance with the JORC Code 2012.
4
Anecdotal evidence from original Novales miners interviewed during the WAI Due Diligence supported with historical
production data from the School of Mines in Torrelavega historical archives
5
4 Anecdotal evidence from original Novales miners interviewed during the WAI Due Diligence supported with
historical production data from the School of Mines in Torrelavega historical archives.
6
Refer to ASX Announcement of 19 December 2019.
2
15
Spain – Guajaraz Zinc-rich Polymetallic Project
The Guajaraz Project is a prospective brown-field zinc-rich polymetallic opportunity with known mineral
occurrences. The project is located in the highly mineralised Central Zone of the Iberian Massif, which ranks
as one of the most mineralised geological units globally and represents the internal zone of the prolific
European Variscan Orogenic belt. Variscan believes Guajaraz represents an excellent, de-risked brownfield
polymetallic project. Reflective of this belief in the prospectivity of this Project, the Company filed an
application with the authorities in Castilla-La Mancha during the year for a 3-year extension of the current
exploration licence over the Guajaraz tenement area. This 3-year extension, covering the period 2023
through 2026 was granted to Variscan Mines’ local Spanish subsidiary, Variscan La Mancha in late October
2023.
FINANCIAL & CORPORATE
CASH
Cash at bank at the end of the quarter was $375,000. The Group continues to enjoy the support of its key
shareholders and the Board is currently in discussions to raise additional capital that it believes will be
successful.
SUMMARY OF EXPENDITURE ON EXPLORATION ACTIVITIES
For the quarter, the Group spent $470,000 on exploration activities, substantively all of which related to the
Group’s Spanish zinc projects. These exploration activities related to:
•
•
•
•
•
Surface and underground drilling;
Geological mapping and modelling;
Technical consulting fees;
Tenement administration, reporting and management; and
Directly-attributable corporate overheads and administration costs.
In accordance with ASX Listing Rule 5.3.2, the Company advises that no Mining Development or Production
activities were conducted during the quarter.
DEFERRED SETTLEMENT SHARES
In accordance with the acquisition of the Spanish Zinc projects, the Company must issue additional shares
upon the satisfaction of certain exploration milestones. These milestones are for the definition, in accordance
with JORC 2012, of an Inferred Mineral Resource (or greater) of:
•
•
•
Milestone 1: 4 million tonnes at 7% Zn
Milestone 2: 8 million tonnes at 7% Zn
Upon satisfaction of each of these milestones, the Company must issue 27,500,000 ordinary shares
to the vendors of Slipstream Spain Pty Ltd and Slipstream Spain 2 Pty Ltd, and 2,426,471 shares to
Hispanibal S.L. as the vendor of the “Hispanibal Option”, for a total of 59,852,941 Ordinary Shares if
both milestones are met.
There is currently no obligation to issue the milestone shares.
16
OTHER
During the quarter, the Company made payments to related parties of $38,000, represented by
remuneration paid to Directors.
ENDS
This ASX announcement has been authorised by the Variscan Mines Limited
For further information, please contact:
Variscan Mines Limited (ASX:VAR)
Stewart Dickson
Managing Director & CEO
E: stewart.dickson@variscan.com.au
T: +44 (0) 7799 694195
Media & Investor Enquiries
The Capital Network
Julia Maguire
E: julia@thecapitalnetwork.com.au
P: +61 2 8999 3699
About Variscan Mines Limited (ASX:VAR)
Variscan Mines Limited (ASX:VAR) is a growth oriented, natural resources company focused on the acquisition,
exploration and development of high-quality strategic mineral projects. The Company has compiled a portfolio of highimpact base-metal interests in Spain, Chile and Australia. Its primary focus is the development of its advanced zinc
projects in Spain. The Company’s name is derived from the Variscan orogeny, which was a geologic mountain building
event caused by Late Paleozoic continental collision between Euramerica (Laurussia) and Gondwana to form the
supercontinent of Pangea.
To learn more, please visit: www.variscan.com.au
For more information
Follow us on LinkedIn
Follow us on X (formerly Twitter)
Visit our investor website: www.variscan.com.au
17
COMPETENT PERSONS STATEMENT
The information in this document that relates to the Exploration Target, exploration results and technical information
is based on, and fairly represents information and supporting documentation reviewed by Dr. Mike Mlynarczyk,
Principal of the Redstone Exploration Services, a geological consultancy acting as an external consultant for Variscan
Mines. Dr. Mlynarczyk is a Professional Geologist (PGeo) of the Institute of Geologists of Ireland, and European Geologist
(EurGeol) of the European Federation of Geologists, as well as Fellow of the Society of Economic Geologists (SEG). With
over 10 years of full-time exploration experience in MVT-style zinc-lead systems in several of the world’s leading MVT
provinces, Dr. Mlynarczyk has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the
December 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves” (‘JORC Code’). Dr. Mlynarczyk consents to the inclusion in the report of the matters based upon the
information in the form and context in which it appears.
Where reference is made to previous releases of exploration results and mineral resource estimates in this
announcement, the Company confirms that it is not aware of any new information or data that materially affects the
information included in those announcements and all material assumptions and technical parameters underpinning the
exploration results and mineral resource estimates included in those announcements continue to apply and have not
materially changed.
Reference is made to the following ASX announcements: 29 January 2024; 19 February 2024; 4 March 2024; 8 April
2024.
18
LISTING OF TENEMENTS HELD AT 31 MARCH 2024
Tenement
SPAIN – Note 5
Tenement No.
Interest
Joint Venture Details
Cantabria
Buenahora Fraction 1
IP 16.662-01
100%
Buenahora Fraction 2
IP 16.662-02
100%
San José
EC 94
100%
La Torra
EC 512
100%
Tres Amigos
EC 1565
100%
Torpeza
EC 2557
100%
Andrea
EC5220
100%
Andrea-demasía a
EC5374
100%
Es
EC8049
100%
Dudosa
EC8165
100%
Cargadoiro
EC11589
100%
Tres amigos-demasía a
EC11594
100%
Flor del pueblo
EC12942
100%
Torpeza-demasía a
EC12952
100%
Torpeza-3ª demasía a
EC13079
100%
Torpeza-2ª demasía a
EC13080
100%
Flor del pueblo-demasía a
EC13154
100%
Dudosa-demasía a
EC13170
100%
Andrea-3ª demasía a
EC13175
100%
Andrea-2ª demasía a
EC13176
100%
Cargadoiro-demasía a
EC13260
100%
Ampliación a Matilde
EC13641
100%
Aumentada
EC14238
100%
Campitos
EC14554
100%
Campitos-demasía a
EC14640
100%
Carmenchu
EC14945
100%
Amelita
EC14949
100%
Eloísa
EC14947
100%
Ampliación a Matilde-demasía a
EC14948
100%
Cargadoiro 2
EC14954
100%
Amelita-demasía a
EC14979
100%
Carmenchu-demasía a
EC14980
100%
Eloísa-demasía a
EC14981
100%
Carmenchu-2ª demasía a
EC14982
100%
6º Aumento a porvenir
EC15672
100%
Ampliación a Matilde-demasía a
EC13641-10
100%
Campitos-segunda demasía a
EC14554-20
100%
Cargadoiro 2- demasía a
EC14954-10
100%
Carmenchu-tercera demasía a
EC14980-30
100%
19
Tenement
6º Aumento a porvenir-demasía a
Tenement No.
EC15672-10
Interest
100%
Joint Venture Details
Torpeza-tercera demasía a
EC2557-30
100%
IP 4.203
100%
Rosario 6 1-40
0310259624
10.4%
Note 4
Rosario 7 1-60
0310259632
10.4%
Note 4
Rosario 101
03102N2229
10.4%
Note 4
Salvadora
0310231355
10.4%
Note 4
Abandonara
0310248487
10.4%
Note 4
Note 1
Toledo
Guajaraz
CHILE
Rosario
NEW SOUTH WALES
Willyama
EL 8075
0%
Hillston
EL 6363
39.2%
Native Dog
EL 8236
0%
Note 1
Woodlawn South
ELs 7257 and 7469
0%
Royalty interest only
Junction Dam
EL 5682
0%
Marmota acquired 100% ownership.
See Note 2
Callabonna
EL 5360
49%
Red Metal 51%, can earn 70%
St Pierre
PER
100%
Beaulieu
PER
100%
Perilya can earn 80%, Eaglehawk
9.8%
SOUTH AUSTRALIA
FRANCE
EL
= Exploration License
PER
= Permis Exclusif de Recherche (France)
IP
= Investigation Permit (Spain)
EC
= Exploration Concession (Spain)
Note 1:
Under an agreement with Silver City Minerals Limited, Broken Hill Operations and Eaglehawk Geological
Consulting Pty Ltd Variscan has converted its interest in parts of these tenements to a NSR (Net Smelter
Return).
20
Note 2:
Marmota has earned 100% of the uranium rights only in EL 5682. Variscan has a 0.5% net profits royalty
on production from a uranium mine.
Note 3:
The remaining exploration licenses owned by Variscan Mines SAS (excluding the Couflens PER) have
been conditionally acquired by a new wholly owned subsidiary, Variscan Mines Europe Limited.
Pursuant to the approval for the Subsidiary Sale, the Ministry of Economy and Finance has imposed,
without prior consultation, the compulsory relinquishment of the remaining licenses. The Company has
approved the relinquishment request and has yet to receive a response. The timetable for the
completion of the relinquishment process is unknown.
Note 4:
On 1 July 2019 the Company announced it had successfully renegotiated the terms of the existing
Option Agreement to provide the Company with a participating interest of 10.4%. The Company can
earn up to 90% of the project through payment of amounts totaling approximately US$2.25 million.
21
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Variscan Mines Limited
ABN
Quarter ended (“current quarter”)
16 003 254 395
31 March 2024
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date (9
months)
$A’000
-
-
(5)
(14)
(b) development
-
-
(c) production
-
-
(d) staff costs
(38)
(112)
(e) administration and co
Share your feedback